MasterCard® PayPass™ Contactless Transit Pilots Installation Guide Table of Contents Revision History ................................................................................................................ 3 1 Introduction........................................................................................................... 4 1.1 Background........................................................................................................ 4 1.2 Scope ...................................
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 4.5.1 Hardware Installation ................................................................................ 30 4.5.2 Functional Test ......................................................................................... 30 5 Terminal Application Functions.............................................................................. 32 5.1 Application Files ............................................................................
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 1 Introduction 1.1 Background In summer 2006, MasterCard commenced a pilot, the purpose of which was to test the feasibility of utilizing the PayPass architecture to allow customer access to the underground transit system at select sites throughout the New York metropolitan area.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 2 New York MTA Subway Upgrade This procedure defines how to perform an upgrade to a phase 1 pilot installation to the phase 2 pilot installation. It does not define how to install the phase 2 installation into a subway turnstile from scratch. 2.1 Background Phase 1 of the pilot comprised the installation of a Secura and contactless card reader in subway turnstiles on the New York subway.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 2.5 Upgrade Process References annotated [value] in this section are to the assemblies / items defined in section 2.2. 2.5.1 Stage 1 – Remove Existing Phase 1 Hardware The first stage of the upgrade is to remove the existing phase 1 solution. 2. Open the top of the turnstile to reveal the phase 1 installation, as shown. 3. Power down the terminal by unplugging in the 3-Pin plug.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 4. Carefully slide the Secura Integration Module up and out of the turnstile, ensuring that the assembly is disengaged from the sprung bushes. 5. Rest the Secura Integration Module resting on top of the on the top of the turnstile.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 6. Detach the “Secura to LED Indicator Board Cable” as shown above. 7. Detach the “Secura to Contactless Reader Cable” as shown above. 8. Detach the “Secura to modem cable” as shown above. 9. Remove the Contactless Reader Assembly (interior) by removing 2 screws as shown to the right.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 10. Remove the Contactless Reader Assembly (exterior) by loosening the 4 fixing bolts as shown below – retain the bracket and washer for fixing the new hardware.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 11. Disconnect the ribbon cable connecting the Contactless Reader Assembly (exterior) and Contactless Reader Assembly (interior). 12. The Contactless Reader Assembly (interior) can now be removed. 13. The Contactless Reader Assembly (exterior) can now be removed, as shown below.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 14. Removal of the phase 1 hardware is now complete. 15. Ensure that you retain the bolts, bracket and washer, as you will need these for the phase 2 installation. .
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 2.5.2 Stage 2 – Fixing Phase 2 hardware to the Mounting Plate 1. You will need to retain the Secura mounting plate, as it is required to mount the phase 2 solution. Remove the 4 bolts left and right of the Secura, (see below) taking care to retain the bolts for fixing the phase 2 solution. 2. Attach the adapter plate [3] to the mounting plate. 3. Attach the phase 2 Secura Control Unit [2] to the adapter plate [3]. 4.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 2.5.3 Stage 3 – Installing the Phase 2 hardware 1. Select the Contactless Reader Assembly [1]. Ensure that the OTI Reader cable [4] and the LED Board cable [5] are attached to the card reader assembly. 2. Position so that the attached cable assemblies can be fed through the second lowest square aperture on the front of the turnstile, as shown. Feed the two cable assemblies through the aperture. 3.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide NOTE PLEASE ENSURE THAT THE POWER CABLE IS NOT PLUGGED INTO THE 3-PIN SOCKET BEFORE THE NEXT STEP. 4. Attach LAN cable [6] to the connection point in the turnstile. 5. Rest the Secura on the top of the turnstile. 6. Attach the Secura Control Unit Assembly [2] to the LED Indicator Board Cable [5] as shown above. 7. Attach the Secura Control Unit Assembly [2] to Secura to Contactless Reader Cable [4] as shown above. 8.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 20. Position the keyholes on the bracket on the rear of the Secura so that they engage with the Sprung Mounting Bushes on the turnstile itself. 21. Carefully slide the Secura down until the key holes engage fully against the sprung bushes and the assembly is secure. The completed installation should look like: 22. Physical installation of the hardware is complete. Power up the terminal by plugging in the 3-Pin plug. 23.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 3 New Jersey and New York MTA Bus Installations This procedure defines how to install the phase 2 pilot solution in the bus environment. The solution comprises the card reader assembly, which is installed at the agreed point on the bus where the consumer can tap his / her card, and the Secura Control Unit Assembly, which is installed out of site.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 3. Please ensure that an inspection of the bus has been performed by the transit agency, and all problems noted, before you accept responsibility for the bus. This is an important step. 4. The Secura is pre-loaded with the application software.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 3.4 Installation Process The Installation process comprises six main parts, as outlined in the following sub-sections. 3.4.1 Install the Antenna 1. Ensure that the area where the antenna is to be positioned is cleaned. 2. Drill a hole on the bus roof – position to be agreed between installer and transit agency, with a view to ensuring best placement relative to internal situation of solution. Note that the antenna cables are 15 feet 3.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide CONFIDENTIAL Version A Page 19 of 37
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide Point 1 CONFIDENTIAL Point 4 Version A Point 5 Page 20 of 37
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 3.4.2 Run the Interconnect Cable The Interconnect cable joins the Secura Control Unit Assembly and the Contactless Reader Assembly. 1. Cut a sufficient length of 12-way multi-core cable to allow it to be comfortably run between the sites of the Secura Control Unit Assembly and the contactless card reader assembly. Note that the maximum length of cable connecting the Secura and the Contactless Reader shall be no more than 15 feet. 2.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 3.4.3 Install the Secura Control Unit 1. Attach the support bracket [8] to the agreed position on the bus, as shown: 2. Cut about 15cm (6in) of flexible tubing 3. Feed the antenna cables through the flexible tubing 4. Feed the power cables through the flexible tubing 5. Feed the cables into the support bracket as shown. The 12-way connector cable shall be fed through the left aperture.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide CONFIDENTIAL Version A Page 23 of 37
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide CONFIDENTIAL Version A Page 24 of 37
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 6. Connect the 12-way multi-core to the Secura Control Unit Assembly, using the following diagram as a guide. Cut Back Tail of 12cm on the 12 way multi core cable Connect Brade to Gnd Terminal Strip 12 way cable 1 Black 2 Red 3 Black (+8.6V) 4 Red (Rx) 5 Yellow (gnd) 6 Green (Tx) 7 Brown 8 Yellow 9 Red 10 Green 11 Black 12 Orange Speaker Card reader LED indicators Wiring for Bus Controll Unit 7.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 3.4.4 Install the Contactless Card Reader Assembly The fixing points / metal tubing will be pre-installed. 1. Remove the clamps 2. Remove the 4 screws from the base of the unit 3. Prise the bottom away from the tube, revealing the connectors 4. Feed the 12-way cable through the grommet on the base of the assembly. 5. Connect the 12-way multi-core to the Card Reader Assembly, using the following diagram as a guide.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 9. Clamp the contactless card reader into the desired position on the bus, as shown to the right.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 3.4.5 Functional Test 1. Have the bus apply power to the solution. Ensure that the Secura powers up correctly and the LEDS light up on the contactless card reader assembly. The Secura display will display a couple of events, namely: o Event 20 – power up o Event 23 – In Service 2. A number of self-tests can then be carried out using the keyboard functions of the Secura. Refer to section 5 for full details of the available functions.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 4 New Jersey PATH Rail Installation This procedure defines how to perform an installation of the phase 2 solution into a NJ PATH Rail subway turnstile and CAM. 4.1 Background For NJ PATH Rail installations, the solution is to be fitted within a cabinet, the CAM, which stands adjacent to the turnstile.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide NOTE PLEASE ENSURE THAT THE POWER CABLE IS NOT PLUGGED INTO THE 3-PIN SOCKET BEFORE INSTALLATION COMMENCES. 4.5 Installation Process The Installation process comprises the following steps. 4.5.1 Hardware Installation 1. Open the CAM door. 2. Fix the Secura Control Unit Assembly to the shelf within the CAM. 3. Drill 4 holes on the right door of the CAM using the template supplied. 4.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide f. Test that communications with the Transit Payment Platform Batch Server can be established by performing function 45. g. Ensure that the terminal is taken out of diagnostic mode by performing function 10. h. Other available test functions can be performed – refer to section 5 for full details of the available functions. 4. Close the CAM – the solution is ready for use.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 5 Terminal Application Functions The terminal application supports a number of simple manual functions to trigger certain events on the terminal as follows: Enter the desired two digit code to select the desired function. For example, to drop the application to MONITOR, press ‘19’ followed by ENT and the application will terminate, passing control to the firmware MONITOR program.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide Function Code Function Name Description 42 Process PAN file This function code processes a list of PANS from a file Test LANG4 Network Card This function code checks whether LANG4 card is working correctly or not.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide Function Code 59 60 CONFIDENTIAL Function Name Description Show GPS Coordinates Displays the current GPS coordinates (only available in bus deployed environment) Upgrade LANG4 firmware Initiates the LANG firmware upgrade. Will prompt the user to enter the FTP server IP address which is hosting the LANG firmware image file (imagez.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide 5.1 Application Files The following files require to be loaded: Software/Application modules’ names are as listed below: DIAGN.PGM LANG4.PGM BATCH.PGM BINCHK.PGM CALLMNGR.PGM CONFIG.PGM DIRECTOR.PGM The main application module EVTLOG.PGM GPS.PGM Handles the GPS functionality in the bus environment ISO8583.PGM LANGDATA.PGM OTICARD.PGM PASSBCK.PGM PROTMNGR.PGM SECURITY.PGM TXN.PGM UI.PGM Configuration files’ names are as below: IDENTITY.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide GPS.CRT ISO8583.CRT LANGDATA.CRT OTICARD.CRT PASSBCK.CRT PROTMNGR.CRT SECURITY.CRT TXN.CRT UI.CRT When loaded as outlined in the previous section, the terminal will attempt to contact the MasterCard Management System (MMS) to pick up its individual configuration. The MMS contact details are held in the IDENTITY.CFG file. MMS must therefore have been setup to expect the contact from each terminal.
MasterCard® PayPass™ Contactless Transit Pilots Installation Guide Appendix A MONITOR Functions If the application is running perform a function 20 followed by a function 19 to drop into the MONITOR program. Effectively the User Interface of the terminal firmware, the Monitor program provides several useful functions, as follows. In MONITOR mode the terminal display will read SECURAPP MONITOR and show the date and time. To scroll through the various MONITOR functions, press the ‘1’ key.