STEP 21: INSTALLATION OF RIDGE CAP
RIDGE CAP WILL COME IN 10’-6” LENGTHS. YOU WILL OVERLAP PIECES 6” UNTIL YOU GET TO THE OTHER
END OF THE BUILDING WHERE YOU WILL TRIM THE LAST PIECE TO FIT. THE RIDGE CAP SHOULD OVERHANG
THE GABLE TRIM 1/2” AT BOTH ENDS OF THE BUILDING.
Place a piece of Ridge Cap on the peak of the building. Center it and make a mark at the lower edges at the end of the
building. Do the same thing at the opposite end of the building and snap a chalk line between the marks. This will make
the Ridge Cap easier to line up and provide a measuring point for locating Butyl Sealing Tape and Outside Foam Closure
Strips.
Apply a bead of Butyl Sealing Tape to the roof panels the full length of the building 3/4” up from the chalk lines on both
sides of the roof. Now, press Outside Closure strips to the Butyl Tape all the way down the building on both sides of the
roof. The edge of the Closure should be 1/4” up from the chalk line.
Install the first piece of Ridge Cap on the peak at the back of the building. Let the Ridge Cap overhang the Gable Trim by
1/2”. Fasten with 1” Painted, Self-drilling Screws through the edge flange and into the top of every other major rib. Run
two beads of butyl tape at the end of the first piece of ridge cap to seal it to the next overlapping piece of Ridge Cap. Lap
the next piece of Ridge Cap 6” over the first, press the seam together and so on down the building. The last piece should
overhang the Gable Trim at the other end of the building 1/2”.
PENCIL MARK
EDGE OF RIDGE CAP
1/4”
FOAM CLOSURE STRIP
3/4” FROM CHALK LINE TO
BUTYL SEALANT
TO CLOSURE
1/2”
SCREWS EVERY OTHER MAJOR RIB
RIDGE CAP
RIDGE CAP
STEP 19: INSIDE CLOSURE STRIPS AT EAVE
On the inside of the building, install Inside Foam Closure Strips
between the eave trim flange and the roof panels. Peal the strips off
the backing paper, pull down the eave trim flange and work the closure
strips between the flange and the roof panels. The ends of the strips
will interlock at a major rib. Start in one corner and work to the other.
PULL FLANGE
DOWN
FOAM CLOSURE INTERLOCK
2 BEADS OF BUTYL
SEALANT TAPE BE-
TWEEN PARTS AT LAP
JOINT