VIADRUS CLEO WALL BOILER OPERATION AND INSTALLATION MANUAL
Dear customer We thank you that you have bought the VIADRUS CLEO boiler thus having shown your confidence in ŽDB a.s.Bohumín, VIADRUS Heating technology Enterprise. For you to get used to a correct way of handling your new product from the beginning please read at first this manual for its usage .
TABLE OF CONTENTS 1. Manufactured boiler variants............................................................................................................... 3 2. Boiler usage and advantages .............................................................................................................. 4 3. Technical data ..................................................................................................................................... 5 4. Boiler description .............................
2. Boiler usage and advantages VIADRUS CLEO wall boiler with a flow-heater is designated for combustion of low-pressure natural gas. The size of the wall boiler is suitable both for heating the houses, leisure amenities and for reconstruction of the heat sources in individual tenements. The wall boiler output is between 8 and 24 kW.
3.
Tab. č. 2 Thermal – technical parameters Reference conditions 15°C a 1013,25 mbar, dry gas Output for CH [kW] Output for HSW [kW] 8 – 24 8 – 24 [m3.h-1] 0,9 – 2,7 [g.s-1] 21,9/30,9 [l.min-1] [l.min-1] 13 9 CH outlet temperature regulation HSW outlet temperature regulation [°C] [°C] 30-85 30-60 Efficiency [%] 90-92 [ppm] [ppm] 7-14 20-50 [°C] 130°C Fuel volume flow Mass rate of flue gases min./max. HSW flow ∆T 25°C HSW flow ∆T 35°C CO NOx Combustion gases temperature 4.
pump. On the internal heating water outlet there is installed an emergency thermostat , a pressure switch and a clack-valve of the manometer for signalling the pressure in heating system. The emergency thermostat will shut down the wall boiler once the temperature has exceeded 95°C. The pressure switch will shut down the wall boiler once the pressure in heating system has dropped below 0,8 bar. Then in the boiler at the heating water input into the boiler there is installed a safety valve.
Fig.No.1 VIADRUS CLEO T boiler assembly Legend(down from top): HSW temperature sensor/ air manostat/ bleeder valve/exhaust ventilator/ Expansion tank/CH temperature sensor/ flue gases collector/ heat exchange/emergency thermostat/ionisation .
ignition electrode/ burner/supporting frame/ pressure switch/ circulation pump/ Honeywell gas valve/ safety valve/refill valve/ HSW flow sensor Legend( down from top): Legend(down from top): HSW temperature sensor/ flue gases thermostat/draught diverter/ bleeder valve/ Expansion tank/CH temperature sensor/ heat exchange/emergency thermostat /ionisation .
Fig.No.2 VIADRUS CLEO K boiler assembly 4.2. Control elements Boiler control front panel The thermometer measures the outlet water to the central heating. The manometer measures the pressure in central heating. By means of a button for setting the heating temperature the user sets the heating water in the system being heated in the range from 35 to 85 °C. The recommended range is from 55 to 85 °C.
1. Burner control unit – ignition and ionisation (ACCF) Electronic device for flame operation and control, for a direct burner ignition by means of a sparkle induced by the electric discharge and monitoring of flame presence by means of ionisation phenomenon.
- emergency thermostat connection regime selection in operation and the reset by means of rotating position switch positioned on the board.
CHARAKTERISTIKA TŘÍRYCHLOSTNÍHO ČERPADLA NYL 53-15 6 VÝTLAČNÁ VÝŠKA (m) 5 4 r3 r1 r2 r3 3 r2 2 r1 1 0 0 0,5 1 1,5 2 2,5 3 3,5 4 4,5 PRŮTOK (m3/h) Legend: NYL 53-15 Three-speed pump characteristics flow versus pump lift Pump blocking function After 24 hours of inactivity the pump is activated for 150 seconds. After the electricity supply interruption there appears the first cycle against the pump blocking after the 3rd hour of inactivity.
BERTELLI automatics function If there is a short-circuited space thermostat, the pump keeps running ( though the boiler is switched off). The pump runs because the boiler still receives the demand on heating and drives the water into the system. Even if the boiler is switched off by the space thermostat the pumps runs after that for 180 seconds.. Parasitic flame ( the ionisation detects the flame before the ignition) can happen at the situations like the gas valve failure.
Current regulation range for a slow ignition Current regulation range of max heating output Electric parameters of heat probe Resistance at 25 °C B ( 25 – 80°C) Insulation resistance 0 – 80% I max 0 – 100% I max 10k + 1% 3435 + 1% 10 mΩ A 500VDC RT – Resistance at the required temperature RTO – Resistance at 25°C T, TO – temperature in K RT = RTO x e The temperature of resistance dependence on Tempera Resistan Tempera Resistan Tempera Resistan Tempera Resistan Tempera Resistan ce ce ce ce ce ture ture tu
Fig. No. 4 Amplifier sensitiveness measuring circuit Table of values ( 230V~ 50 Hz) Start ON Ionisation current U ( µA) < 0,6 + 10% Flame resistance ER ( >140 + 10% mΩ) Ignition Ignition voltage Ignition electrode distance Sparkle repetition frequency Ignition cable maximum length Ignition transformer Work schedule and times Auto-test time Safety time Safety time operating tolerances Reaction switching-off operation ON >1,2 + 10% <70 + 10% operation OFF >0,9 + 10% <95 + 10% approx.
P1 – heating position switch P3 –HSW temperature setting P2 –CH temperature setting P4 – max. output to CH No..
Legend: (down from top): HSW flow sensor/HSW thermal probe/SH thermal probe/modulator/pressure switch/manostat/space thermostat/network supply-phase/ zero conductor/ ionisation electrode/pump( brown, blue, blue, brown)/ventilator/ignition electrode/gas valve(brown, blue) /emergency thermostat P1 – position switch P2 –CH temperature setting P3 –HSW temperature setting P4 – max.
No..
5. Positioning and installation 5.1. Regulations and guidelines a) regarding the heating system ČSN 060310 : 1998 Central heating and assembly ČSN 060830 : 1996 Safety devices for central heating and HSW heating ČSN EN 483 : 2000 Gaseous fuels boilers for central heating - Boiler in design C with nominal heat intake max. 70 kW ČSN EN 297:1996 Gaseous fuels boilers for central heating - Boiler in design B11 and B11BS with atmospheric burners with nominal heat intake max.
5.2 Installation conditions Only a firm authorized for boilers installation is allowed to install VIADRUS CLEO gas boiler on the basis of the designer ´s approved documentation. Before the installation the assembly firm is obliged to make a correct boiler choice with regard to its functional characteristics and required parameters. The boiler has IP 41 protection which guarantees the resistance against the vertically dripping water. Therefore it can be installed in bathrooms in zone 3 ( in the distance min.
Fig. No. 7 Boiler main dimensions 5.3. Positioning The boiler positioning must correspond to the project documentation. The boiler is positioned in a way making sure that the necessary operating conditions are ensured. (VIADRUS CLEO K ,the boiler with open combustion chamber or VIADRUS CLEO T, the boiler with closed combustion chamber ), this with regard to the volume of brought combustion air and the flue gases exhaustion.
Boiler positioning with regard to the fire regulations: A safe distance from the combustible materials − When installing and operating the boilers it is necessary to keep a safe 200mm distance from combustible materials with combustibility degrees B, C1 a C2 (according to ČSN 06 1008 : 1997) − For easily flammable materials with combustibility degree C3, which burn quickly and by themselves also after the ignition source removal (like paper, millboard, stiff paper, asphalt and tar boards, wood and fibreboar
Fig. No. 8 Boiler console for suspension on the wall. Fig. No.
6. Commissioning 6.1 Connection to the system 6.1.1.Connection to the heating system and filling with water VIADRUS CLEO boiler is designated for heating systems with a forced circulation . The water flow speed can be set by the selection of pump revolutions switch. The heating system must be thoroughly flushed out before filling with water in order to wash out al impurities that can be deposited in distribution pipes or heating bodies and can result in damaging the pump.
Before the gas pipes connection to the boiler the gas pipes must be tested and revised. All gas joints after their connection to the boiler must be tested using a gas detector or foaming solution. Maximum natural gas inlet pressure is 20 mbar. The gas pipes threaded joints must never be strained by additional forces. 6.1.3.Connection to the electricity network The boiler is equipped with a movable three-core cable. It is connected to the network socket positioned maximum 1 m from the boiler.
6.2. Boiler commissioning The whole installation must correspond to the relevant regulations for this equipment. The boiler must be compatible with local connecting conditions (check of adjustment status on the serial number plate ). The boiler commissioning can only be done by organizations authorized for it and trained by the manufacturer.
Legend: Modulation regulator cover / Modulation regulator/ Gas pressure on the nozzle measurement/ gas inlet pressure measurement/ modulation regulator Fig. No. 11 Modulation regulator - In case of setting of min. and max pressure on the nozzle it is necessary to take following steps: a) dismount the modulation regulator cover b) set the position switch on the control panel into the position of CH + HSW and P4 trimmer which is positioned on the el. board reset it into the right limit position (min.
is obliged to acquaint the user with the boiler operation. The user by his signature in the guarantee certificate confirms that he was acquainted with boiler operation. The boiler itself is in operation secured against the dangerous conditions. But it cannot prevent from the failures the reason of which isn’t included in the boiler mechanism.
Behaviour in case of a failure: In case of a flame simulation the ignition is prevented. Note: If GMF unit at the flame control detects the flame simulation, it reports the defect and if the simulation lasts for longer than 15 seconds the demand on heat is stopped (the heat is switched off by the relay related to the heat demand) and a new ignition can only be attempted after the system reset via the regimes position switch.
The boiler is fully automatic and is isn’t recommended to disconnect it from electricity The boiler is equipped with automatic protection against freezing It is forbidden to interfere with the secured parts Close to the boiler and smoke flues there must never be put, stored or hung any objects made of combustible materials ( the safe distance between the appliance and the combustible materials in the direction of the main radiation is 50 mm, in other directions 10 mm) There
10. Guarantee and liability for defects Závod topenářské techniky VIADRUS provides: – The boiler guarantee for 24 months after the date the product has been put into operation, but maximum 30 months after the date of dispatch from the manufacturing factory. The manufacturer requires for the guarantee applicability : – In sense of Act no. 222/94 Coll.
ŽDB a.s.ZTTVIADRUS Intended for user Guarantee certificate and Quality and completeness certificate for VIADRUS CLEO… boiler Boiler serial number ..............................….. Boiler output ............................... The way of smoke-flue connection ..............................….
ŽDB a.s.ZTTVIADRUS Intended for service organization Guarantee certificate and Quality and completeness certificate for VIADRUS CLEO… boiler Boiler serial number ..............................….. Boiler output ............................... The way of smoke-flue connection ..............................….
ŽDB a.s.ZTTVIADRUS Intended for manufacturer Guarantee certificate and Quality and completeness certificate for VIADRUS CLEO… boiler Boiler serial number ..............................….. Boiler output ............................... The way of smoke-flue connection ..............................….
Annex to the guarantee certificate for customer- the user Record date Record of accomplished guarantee and after-guarantee repairs and regular product checks Carried out activity Contracting service Customer ´s signature organization (stamp, signature)
31
32