Technical information

12
2.4 Delivery and accessories
Boiler is delivered according to the purchase order on the pallet, where the whole boiler drum is placed and
on the sides it is attached the wrapped boiler shell. The accessories are put inside the boiler drum,
accessible by opening the stoking door. The boiler is packed in a transport package and must not be tilted
over during the transport
Standard boiler delivery:
Boiler on the palette with due number of cells
Cover including ash pans and small ash pan in corresponding size
Thermo-manometer (1 pc)
Input and output cock Js 1/2“ (1 pc)
Draught regulator complete for size 3 – 7 cells (1 pc), for size 8 - 10 cells (2 pcs)
Blind plug Js 6/4“ (1 pc)
Sealing under plug (1 pc)
Screw of stifling system (1 pc)
Magnetic element (1 pc)
Cover handle (1 pc)
Plastic ball (1 pc)
Connecting material for covers (see chapter 2.5)
Connecting material for pull rod of the smoke socket (see chapter 2.5)
Pipe of heating and recurrent water 6/4“ (2 pcs)
Cleaning tools (hook, brush with handle, tang, holder for cleaning tools)
Handling spanner (1 pc)
Box spanner with hex handle 902-13 (1 pc)
Manufacturing plate (1 pc)
Business and technical documentation
Necessary accessories: (is not included in delivery):
Two way safety valve DBV 1 – 02 (1 pc) incl. siesal (10 g); this equipment has not to be used in case of
open heating system
Safety valve – 1 pc
By request (is not included in delivery):
Filter 3/4“ – for delivery with the two way safety vent DBV 1 - 02
The necessary accessories and optional boiler accessories is not included in the boiler standard
price.
2.5 Assembly technique
Installation of the boiler body – two way safety valve DBV 1 -02
1. Fit the boiler drum on the retaining wall (substruction).
2. Mount to the boiler drum system outlet the connecting tube G 6/4“, connect the second end with heating
system.
3. Mount to the boiler drum system outlet the connecting tube G 6/4“, and connect the second end with the
heating system.
4. To connect two-way safety valve DBV 1 - 02 with connecting pipe of recurrent and heating water and with
the input of cold water and with the output of excessive heat according to Fig. no.10.
5. Mount the discharging valve to 1/2“ thread in connecting tube of heating water according to Fig. no. 3.
6. Set the smoke tube to the smoke adapter and insert it into the chimney. The diameter of smoke tube is
160 mm for sizes with 3 7 sections and pro sizes 8 – 10 sections it is 180 mm.
7. Screw the draught regulator into the opening in upper part of front section. The boiler draught regulator
adjustment procedure is described in the manual enclosed to the particular regulator. For version
with 8 10 sections there are used two draft controllers. Draft controller has to be screwed according to
Fig. no. 3 and 4).
8. Blind the threated opening JS 6/4“ in the front section with JS 6/4“ plug. Place the sealing under the plug.