Operating instructions

Note
During commissioning, the combustion control unit carries out an automatic
calibration. Only test the emissions approx. 30 s after the burner has started.
1. Connect a flue gas analyser at test
port A (on the boiler flue outlet).
2. Open the gas shut-off valve, start
the boiler and create a heat
demand.
3. Adjust the lower output.
Constant temperature control
unit:
K + d press simultaneously:
"1" is shown.
Weather-compensated control
unit:
K + d press simultaneously:
"Relay test" and then
"Base load" is shown.
4. Check the CO
2 content. Should the
actual value deviate from the
above ranges by more than 1 %,
implement steps from page 23.
5. Enter actual values into the service
report.
6. Adjust the upper output.
Constant temperature control
unit:
a press:
"2" is shown.
Weather-compensated control
unit:
a press:
"Full load" is shown.
7. Check the CO
2 content. Should the
actual value deviate from the
above ranges by more than 1 %,
implement steps from page 23.
8. After testing, press d.
9. Enter actual values into the service
report.
Further details regarding the individual steps (cont.)
24
Commissioning, inspection, maintenance