18 VMware, Inc.
Primary Select the Data: Replication tab and wait for 
both the File System and the Registry status to 
display Synchronized. Access the vCenter 
Server Heartbeat logs and confirm that no 
exception errors occurred during the 
synchronization process.
Data replication resumes from the 
Secondary server back to the Primary 
server. Both the File System & Registry 
status become Synchronized.
Switchover Exercise This exercise demonstrates the ability to switch the functionality and operations of the active 
server on command to the other server in the pair using the vCenter Server Heartbeat 
Console. Perform this exercise only after successfully completing the Failover Simulation and 
Data Replication Exercises. 
Notify any local users that the service will be unavailable for the duration of the exercise.
Using the System Tray icon, verify that the Secondary server is active (S/A) and servicing 
clients. On the Primary server, verify that the server is passive using the System Tray icon 
status (P/—). On the Secondary server, launch the vCenter Server Heartbeat Console and 
select the Data: Replication tab. Verify that both the File System and Registry status are 
Synchronized.
vCenter 
Server 
Heartbeat 
Console
Click on the Server: Summary tab. Select the 
Primary server icon and click Make Active.
The vCenter Server Heartbeat Console 
Server: Summary page displays the 
applications stopping on the active server. 
Once all applications are stopped, the 
active server becomes passive and the 
passive server becomes active. The 
Console shows the applications starting on 
the newly active server.
Both the File System and Registry status are 
Synchronized.
Any Confirm application performance and 
availability meets previously defined criteria. 
Verify that client applications are running as 
expected after the switchover process.
Services continue to be provided as before 
the switchover occurred. You may need to 
refresh or restart some client applications 
as a result of a switchover.
Table 1-2. Acceptance Verification
Exercise Machine Activity Result