251 UPPER V.B. TO LOWER V.B. BOLTS (21 MM LENGTH)(10 REQUIRED).
252 UPPER VALVE BODY ASSEMBLY.
254 LOWER VALVE BODY ASSEMBLY.
300 MAIN VALVE BODY SPACER PLATE.
850 'MANUFACTURED" (440-T4 PUMP BOLTS) ALIGNMENT DOWELS.
243
850
850
850
243
243
243
95
Copyright © 2010 ATSG
Copyright © 2010 ATSG
Copyright © 2010 ATSG
AUTOMATIC TRANSMISSION SERVICE GROUP
Technical Service Information
VALVE BODY ASSEMBLY (CONT'D)
COMPONENT REBUILD (CONT'D)
21. As you lower the upper valve body and spacer
plate assembly into place, temporarily installed
accumulator bolts will start to automatically
start to move out, as shown in Figure 156.
22. With all of temporary alignment dowels still in
place, hold upper valve body and spacer plate
against the lower valve body, ensuring all small
parts are in place, and then install ten retaining
bolts, as shown in Figure 156.
Note: "Snug" the bolts only, at this time.
23. Start the two temporary accumulator bolts into
the threads below.
24. With all alignment dowels in place, torque the 10
installed valve body bolts to 9 N·m (80 in.lb.), as
shown in Figure 157, beginning in the center and
working outward in a circle.
25. Remove the four alignment dowels and install
plastic check valve in the upper valve body, as
shown in Figure 158.
Continued on Page 96
Figure 156 Figure 158
Figure 157
354 K3 CLUTCH AND ACCUMULATOR CHECK VALVE (PLASTIC).
243 ACCUMULATOR 2 HOUSING TO UPPER V.B. (64 MM LENGTH)
850 'MANUFACTURED" ALIGNMENT DOWELS.