Specifications

Enquiry Specification for Wagon Tippler with Side Arm Charger and Associated works
NRO/CON/WT/533
EPI – New Delhi Volume-2B, Rev.0 Page 31 of 63
21. Operation and maintenance manual.
22. Detailed technical literature / catalogue of manufacturers.
23. Graphic display sheets, report/data generation, fault listing etc.
24. Terminal plan drawings
25. System grounding/ earthing scheme.
26. Application software program listings with detailed documentation.
27. Ladder Logic diagram /Statement Lists and software details.
28. Formats and work sheets for generation and display of overview,
groups, loops, graphics, alarms, operator’s guide messages, real time
and historical trends Log and shift formats.
29. List of drawings & spare parts.
30. Final test & calibration certificates and guarantee certificate / warrantee
certificate.
31. As built Control description with Operational instruction use of various
commands, instruction for control of plant and equipment from Operator
workstation.
32. Drawings/documents for inspection of equipment:
(I) Type test certificate for identical equipment.
(II) Sub-supplier’s/vendor’s catalogue/technical literature.
(IV) Test reports for internal inspection.
(V) Test certificate of components.
(VI) Technical specification & data sheets of equipment.
(VII) All “Approved” drgs./ “Commented” drgs as applicable.
33. Automation systems.
(I) Software including media and documentation.
(II) Description of all components of the user system with functional
description, overview flow diagram, interface listing, mathematical
models, and fault message lists, operator commands, simulation
facilities, etc.
(III) Source code of the user system.
(IV) Object code of the user system.
(V) I/O listing
(VI) Ladder/block diagrams, etc.
(VII) Factory Acceptance Tests & procedures for PLC/DCS
34. Other Drawings/documents :
(I) Operation & maintenance manual.
(II) Catalogues and manuals.
(III) All ”As-built” drawings.
(IV) Soft copies of all drawings.
(V) Technical specification/data sheet of equipment.
(VI) Instructions for storage/erection/testing/commissioning
(VII) Commissioning report.
(e) As-built drawings (Electrical)
Upon installation and commissioning supplier shall incorporate revisions/
modifications if any in the reproducible and submit 'as built' drawings for
purchaser's record as per general condition of contract.
Complete and comprehensive instruction manuals for operation and
maintenance of the equipment with drawings. This shall include the
following: