Instructions / Assembly

1 ¼” WELL POINT
INSTALLATION INSTRUCTIONS
This brochure is designed to provide step-by-step instructional assistance
to the individual who wishes to install a shallow water well system for
residential sprinkler or irrigation. The procedure consists primarily of
“washing” a smooth PVC casing into the water bearing sand layer,
facilitating the insertion of a well point, through which water can be drawn
from this layer. This procedure eliminates the need for professional well
drilling equipment.
Note: This installation is for shallow water only and not recommended for
systems intended for human consumption.
Shallow wells are different in various location. Different sand formations
produce or transmit water at various rates. While some installations may
obtain 10-15 Gallons Per Minute (GPM) from one well, others may require two
or more, wells to obtain the desired GPM.
Plan to install one 4 foot well point per 1/4 H.P. of pump capacity.
For best results plan and lay out the entire system prior to beginning the
actual installation. Select a location which is as close as possible to the
pump location to avoid long suction lines. Be sure to allow adequate area for
multiple wells (if required).
Multiple well points should be kept 5-8 feet apart. Use care in selecting an
area free of overhead obstructions and buried wires.