Boiler Sizing Replacement Guide

3
SECTION 1
PROCEDURE FOR SIZING HOT WATER BOILERS
STEP 1: COMPLETE A JOB SURVEY FORM
Certain key information is required for each
boiler replacement job in order to calculate the
heat loss, select the proper boiler and determine
the selling price. Figure 1 is a Job Survey Form
(part of a Weil-McLain Boiler Replacement
Worksheet) to aid in recording the required
information. It will serve as a checklist of the
basic data for the existing installation and
a permanent record for your job file. Boiler
Replacement Worksheets to be used with this
booklet are available through Weil-McLain
distributors and sales representatives.
FIGURE 1: JOB SURVEY FORM
BOILER REPLACEMENT WORKSHEET
JOB SURVEY FORM
CUSTOMER NAME: PHONE:
ADDRESS:
PREPARED BY: DATE:
PRESENT HEATING SYSTEM:
TYPE OF RADIATION:
HEATING MEDIUM: ¨ Hot Water ¨ Steam
FUEL NOW USED: ¨ Natural Gas ¨ Propane ¨ #2 Oil ¨ Electricity
FUEL TO BE USED: ¨ Natural Gas ¨ Propane ¨ #2 Oil ¨ Electricity
IS SYSTEM HEATING SATISFACTORILY? ¨ Yes ¨ No
If no, what is the problem?
How can it be corrected?
RELOCATE BOILER? ¨ Yes ¨ No If yes estimate time Materials
Corrosive Atmosphere?
PRESENT SOURCE OF DOMESTIC WATER: ¨ Tankless Heater ¨ Indirect Tank ¨ Other
WILL NEW BOILER HAVE A WATER HEATER? ¨ Yes ¨ No Type
HOUSE CONSTRUCTION:
GLASS:
WALLS:
CEILING:
SLAB:
HOUSE DIMENSIONS (Use sketch for accuracy):
High Altitude Ft. Elevation
Basement ‘ H x ‘ L x ‘ W = Sq. Ft.
First Floor ‘ H x ‘ L x ‘ W = Sq. Ft.
Second Floor ‘ H x ‘ L x ‘ W = Sq. Ft.
DESIGN TEMPERATURE DIFFERENCE °F
NEW THERMOSTAT(S) REQUIRED ¨ Standard ¨ Programmable