BASIC INSTALLATION


1. Disconnect the two external wires connected to the boiler
thermostat terminals (see Field wiring, beginning on page30
for terminal locations).
2. Connect a voltmeter across these two incoming wires. Close
each thermostat, zone valve and relay in the external circuit
one at a time and check the voltmeter reading across the
incoming wires.
3. ere should NEVER be a voltage reading.
4. If a voltage does occur under any condition, check and correct
the external wiring. (is is a common problem when using
3-wire zone valves.)
5. Once the external thermostat circuit wiring is checked and
corrected if necessary, reconnect the external thermostat
circuit wires. Allow the boiler to cycle.


1. Inspect the condensate drain line, condensate PVC ttings
and condensate trap. (See page27 for component locations.)
2. Pour water into the top of the boiler’s ½” PVC condensate
tee and check for any leaks in the condensate drain line or
ttings. Repair any leaks.
Fill condensate trap with water
1. Loosen the hose clamp securing the right end of the conden-
sate trap to the PVC reducing elbow (see page27 for details).
2. Slide the trap hose end o of the elbow.
3. Fill the trap with fresh water to within an inch of the end
of the hose.
4. Replace trap hose on PVC reducing elbow and tighten the
hose clamp.
e condensate trap must be lled with water dur-
ing all times of boiler operation to avoid ue gas
emission from the condensate drain line. [Prime
the condensate trap (by pouring water into the
outlet tee while restricting ow in drain tube) if
boiler has been out of service for an extended pe-
riod.] Failure to ll the trap could result in severe
personal injury or death.

Read the instructions to adjust and set up the U-Control
module.
Verify that the boiler model is set correctly in the U-Control,
and that it displays correctly.
Verify that the boiler and system are full of water and all
system components are correctly set for operation.
Fill vent condensate trap with water (by removing hose
clamp and hose at PVC reducing elbow). Replace hose on
PVC reducing elbow and tighten clamp.
Verify electrical connections are correct and securely at-
tached.
Inspect vent piping and air piping for signs of deteriora-
tion from corrosion, physical damage or sagging. Verify
air piping and vent piping are intact and correctly installed
per this manual.

Before starting the boiler, and during
initial operation, use a leak detector or
smell near the oor and around the boiler
for gas odorant or any unusual odor. Re-
move boiler front door and smell interior
of boiler enclosure. Do not proceed with
startup if there is any indication of a gas
leak. Repair any leak at once.
DO NOT adjust or attempt to measure
gas valve outlet pressure. e gas valve is
factory-set for the correct outlet pressure.
is setting is suitable for natural gas and
propane, requiring no eld adjustment. At-
tempting to alter or measure the gas valve
outlet pressure could result in damage to
the valve, causing potential severe personal
injury, death or substantial property dam-
age.
Propane boilers only — Your propane sup-
plier mixes an odorant with the propane
to make its presence detectable. In some
instances, the odorant can fade, and the
gas may no longer have an odor. Before
startup (and periodically thereaer), have
the propane supplier verify the correct