LIFTING & HANDLING
IMPORTANT: Always prepare a Lifting Plan/Risk Assessment.
By Forklift / Tele-handler
Each TCG is fitted with forklift pockets which are designed to allow the
TCG to be raised by a forklift/tele-handler. The TCG can be lifted from all
4 sides. This must be considered in your risk assessment
It is important that the total gross weight of the TCG is not more than half
(50%) of the forklift’s maximum SWL. Ensure that the forklift’s forks are
set to the correct width for the TCG’s fork pockets
By Crane
Lifting of tanks should only be undertaken by a competently trained
person
You will require a lifting device (crane) and suitable four-leg chain slings
fitted with hooks and safety catches
Always check and obtain official confirmation from the chain sling
supplier that it is both suitable in SWL and chain length
With the chain slings correctly attached to the lifting equipment, attach
each hook to the lifting points. Once attached, ensure the catches fitted
to all hooks are closed
Attach tag lines to the base of the unit to control rotation
Lift the chains until taut and check that the hooks are correctly positioned
with catch closed and that the chains are not twisted. If a fault is found,
lower the chain and reattach correctly
Lift the unit until just off the ground and check that it is balanced and
stable. Once you are satisfied that everything is correctly and safely set
up, you can continue with the lift.
The TCG must ONLY be lifted via the dedicated crane lifting
point(s) found in each corner. See Lifting Points
ALL lifting point(s) must be used during a lift
The lifting points MUST be inspected for condition and safe use
DO NOT lift from the base, with polyester slings