4.4  Preparing the System Wiring Diagram 
  Keep a copy of the system-wiring diagram with the SP40S manual as a permanent record of the system 
wiring. 
4.4.1 Unpacking and Taking Inventory 
Carefully unpack the panel and make sure each item described on the packing slip is present and undamaged.  
1.  Check  the  exterior  of  the  shipping  container(s) for  any  exterior  damage,  then  the  interior  of  the 
container(s). 
2.  Notify both the carrier and Cooper Notification immediately on the straight bill of lading (supplied by 
the carrier) if any damage is found both verbally and in writing; you may also request an inspection by 
the carrier. Such requests must usually be made within a specified time period from date of shipment. 
Cooper  Notification  is  not  responsible  for  damage  to  equipment  occurring  during  shipping,  and  only 
furnishes replacement parts against a written purchase order. It is the customer’s responsibility to file a 
claim with the carrier. 
3.  Follow any instructions Cooper Notification and/or the carrier may supply about possible damage. 
4.  If no damage is found, compare the contents of the Inventory List against the contents of the shipping 
container(s), to ensure receipt of all components. 
5.  Save all shipping  materials  (any “bubble wrap” or plastic) for possible future use. Store in a safe, dry 
location. 
4.4.2 Locating the Panel 
Mount  the  panel  in  a  location  within  the  environmental  limits  specified  in  the  latest  UL  Standard  864  for 
indoor/dry control panels. DO NOT locate the panel in a hazardous area. 
CAUTION:  To comply with the latest NFPA and UL requirements for interconnection of fire 
alarm control equipment, locate the SP40S Multi-Function Facility Communication System in 
the same room, and within 20 feet of, a listed compatible fire alarm control panel. Enclose the 
wiring in conduit and connect it properly to such control panel. 
1.  See Figure 4-2 for the panel mounting hole layout. 
2.  Mark and drill mounting holes for appropriate screws and anchors to ensure secure mounting to the type 
of surface at the selected location. 
3.  Prevent dust and dirt contamination of the SP40S Multi-Function Facility Communication System 
during installation.  This contamination can interfere with the operation and  reduce the life of the 
equipment. 
4.  Open  the  door  and  remove  the  dead  front  panel, then  mount  the  SP40S  Multi-Function  Facility 
Communication  System  at  the  selected  location.    Use  care  to  avoid  damage  to  the  module  during 
installation. Do not apply excessive pressure to the PC board or its components, including field wiring 