Installation Manual

Connecting the AC Grid to the Safety Switch
Thisprocedurevariesdependingontheinvertertype(singleorthreephase).Makesureyou
followtheprocedureapplicabletoyourequipment.
IftheSafetySwitchhasapre-assembledRGM(seeFigure21),fliptheRGMplate
downwardsbeforemakingtheconnections.
To connect the AC grid to the Safety Switch – single phase
3-7.6kW inverters:
1. Removethespring-clampterminalinstructionsfrominsidetheswitch.
2. Strip05⁄16''(8mm)oftheACwireinsulation.
3. InserttheACconduitintotheAC-sideknockoutthatwasopened.
NOTE
Connect the equipment grounding before connecting the AC wires to the AC terminal
block.
Veillez à relier le conducteur de PE (la terre) avant de connecter les fils CA au bornier CA.
4. Connectthewirestotheappropriateterminalblocksaccordingtothelabelsonthe
terminalblocks(N,Gnd,L1andL2).
5. Useastandardflat-bladescrewdrivertoconnectthewirestothespring-clampterminals:
l Thescrewdriverbladeshouldfitfreelyintheterminalopening.Toolargeabladecan
cracktheplastichousing.
l Insertthescrewdriverandpressthereleasemechanismandopentheclamp.
l Insertthewireintotheroundopeningandremovethescrewdriver–thewireis
automaticallyclamped.
Figure 26: AC Spring-clamp terminal example - single phase 3-7.6kW inverter
6. Verifythattherearenounconnectedwires.
SolarEdge-Installation Guide MAN-01-00002-4.0
38
Connecting the AC Grid to the Safety Switch