Installation Guide

Adding, Removing, or Replacing Power Optimizers
1. TurnOFFtheinverterON/OFF/Pswitch,andwaituntilthegreenLEDisblinking,indicatingthatthe
DCvoltageissafe(<50V),orwaitfiveminutesbeforecontinuingtothenextstep.
2. DisconnecttheACtotheinverterbyturningOFFthecircuitbreakersonthedistributionpanel.
3. TurnOFFtheSafetySwitch.
4. Disconnectandconnectthenecessarypoweroptimizers.
5. PerformpairingandotherproceduresdescribedinActivating,CommissioningandConfiguringthe
SystemUsingtheInverterSetApponpage33onallinverterstowhichpoweroptimizerswereadded
orfromwhichpoweroptimizerswereremoved.
6. Inthemonitoringplatform,usetheReplacebuttoninthelogical layouttab(insite
Admin).Replacetheserialnumberoftheremovedpoweroptimizerwiththeserial
numberofthenewlyinstalledpoweroptimizer.Referto
https://www.solaredge.com/sites/default/files/se-monitoring-portal-site-admin.pdf
-Single Phase Inverter with HD-Wave Technology Installation MAN-01-00541-1.0
62
Adding, Removing, or Replacing Power Optimizers