Installation Manual

3
1. Introduction
1.1 Purpose
This document provides detailed instructions and valuable safety information regarding the installation, electrical connection,
and maintenance of following Chint Solar Crystalline Photovoltaic modules:
CHSM6608M CHSM6610M CHSM6610M(BL) CHSM6610M(FR)
CHSM6612M CHSM6610P CHSM6610P(BL) CHSM6610P(BF)
CHSM6610P(FR) CHSM6612P CHSM6612P(FR)
CHSM6608M/HV CHSM6610M/ HV CHSM6612M/HV
CHSM6612P/HV DIAMOND CHSM6612P/HV
All the instructions should be read and understood before installation. The installers should be trained and conform to all
safety precautions in this guide when installing the module. Keep this guide in a safe place for further reference.
1.2 Limitation of Liability
Because the use of this manual and the conditions or methods of installation, operation, use and maintenance of photovoltaic
(PV) products are beyond Chint Solar’s control, Chint Solar does not aord the responsibility and expressly disclaims liability
for loss, damage, or expense arising out of or in any way connected with such installation, operation, use or maintenance.
Chint Solar reserves the right to change the manual without prior notice.
1.3 Precautions of Installation
1.3.1 Module’s unpack and transfer
a) When the whole pallet of modules are delivered to the site and unloaded, make sure the safety of the module especially if
it needs to be lifted in the roof projects. Put it into the protect device and then lift it to the roof in case of bumping against the
wall during the lifting process.
b) Firstly, tear the stretch lm, then move away the top cover after cutting o each module packing strip while unpacking.
Two operators work as a group, grasp the module frame tightly in the same direction and take out the module one by one. It
is a must that the operators rive the adhesive tape of the xed module one by one, rive one piece and then take out one piece
of module. We don’t allow to rive all the adhesive tape one time in case that the whole pack topples and falls down. The whole
process must be taken very gently. Don’t collide with any hard object or let any parts of the frame touch and drag on the
ground.
c) After unpacking the modules should be installed that day as far as possible. Its recommended to take the right amount of
modules according to the progress of the project every day. Due to the modules piling on the ground after unpacking, in case
of heavy rain and other inclement weather which has the potential risk to be a long soak in water can aect product reliability,
such as typhoons and other modules in case of inclement weather is not installed which may be torn away. If the users need to
store modules before installation, do not open the package, the goods should be stored in a room temperature, dark, dry and
ventilated place.
1.3.2 Module’s Stack
a) When a module is taken out of the box, cardboard bedding below should be applied, in order to avoid contacting cement
surface / ground hard metal or steel tile shocked collision friction scratch.