Installation Guide

NOTE
ASolarEdgeinvertermaybeinstalledinasitewithagenerator,howevermustnotoperateat
thesametimeasthegenerator.
Operatinganinverterandageneratorsimultaneouslywillvoidthewarranty.SolarEdgerequires
installingaphysicalorelectronicinterlock,whichwillpreventthegeneratorandinverterfrom
operatingsimultaneously.Interlockprocurement,installation,maintenanceandsupportare
theresponsibilityoftheinstaller.Damagetotheinverterduetoincorrectinterlockinstallation
oruseofaninterlockthatisincompatiblewiththeSolarEdgesystemwillrendertheSolarEdge
warrantyinvalid.
IMPORTANT SAFETY INFORMATION
To perform Rapid Shutdown, shut down AC power to the inverter. This can be done by turning off the
AC breaker in the main service panel, which is an approved AC disconnect as described in the NEC.
IMPORTANTSAFETYINSTRUCTIONS
-Single Phase Inverter with HD-Wave Technology Installation MAN-01-00541-1.0
9