Installation Guide

Verifying the Connection
Afterconnectingandconfiguringacommunicationoption,performthefollowingstepstocheckthat
theconnectiontothemonitoringserverhasbeensuccessfullyestablished.
1.
AccesstheStatusscreen:
a. IfnotalreadyON-turnONACtotheinverterbyturningONthecircuitbreakeronthemain
distributionpanel.
b.
OpenSetAppandfollowtheinstructionsonthescreen(scantheinverterbar-code;movethe
ON/OFF/PswitchtoPposition(forlessthan5sec)andrelease).
ThemobiledevicecreatesaWi-Ficonnectionwiththeinverteranddisplaysthemain
Commissioningscreen.
2.
CheckthatS_OK-Server Connectedstatusappearsinthemaininvertersection:
Status
Inverter
SN 07318000C
Power Voltage Frequency
Optimizers Connected
S_OK
Server Connected
Status
Production
Switch
ON
CosPhi
1.00
Limit
No Limit
Country
USA2
Voltage Temp Fan
Commissioning
3.
ScrolldowntotheCommunicationsectionandcheckthatthecommunicationoptionsareas
required.FormoreinformationrefertoCommunicationStatusonpage40.
Communication
LAN
Connected
RS485-1
SE Slave
NC
RS485-2
Modbus
2 of 2
Cellular
N/A
Wi-Fi
NC
ZigBee
NC