3.4. Site Prerequisites
Site survey
Site survey should be done before start the installation taking in
consideration the following:
Premises information
• Site details (address, contact persons, GPS and/or map co-ordinates, etc.).
• Site access and storage information (means of transport, equipment
storage and lifting information, etc.).
• Site location maps.
Network planning
• Site Coordinates.
• LOS verification (Hub – TS).
• Rooftop information (height, status, access, dimensions, layout, etc.).
• Information about pre-existing indoor/ outdoor equipment.
• Available mounting space (on the buildings’ roofs) to reserve for the
installation of the outdoor equipment.
Site-specific information
• Mechanical specifications of masts/ towers (type, dimensions/ diameter,
material, exterior finishing, etc.).
• Location of appropriate grounding points (bar or terminals).
• Location of appropriate power supply distribution points.
• Location of cable conduits available for routing the cables.
• Location of the network port distributors.
• Total length of the cables required.