Manual

1
2
1 2
Fig. 14: Connection compartment double chamber housing Ex d
1 Spring-loaded terminals for power supply and cable screen
2 Ground terminal for connection of the cable screen
Fig. 15: Wiring plan double chamber housing Ex d
1 Voltage supply/Signal output
5.6 Switch on phase
After connecting IPT-10 to power supply or after a voltage recurrence,
the instrument carries out a self-check for approx. 30 seconds:
l Internal check of the electronics
l Indication of the instrument type, the rmware as well as the
sensor TAGs (sensor designation)
l Output signal jumps briey (approx. 10 seconds) to the set fault
current
Connection compart-
ment
Wiring plan
Switch on phase
20 Process pressure transmitter IPT-10 Vers. 2.0 - ceramic sensor 4 20 mA/HART
5 Connecting to power supply
31540-EN-090130