11 Service and maintenance continued
o Check/test. . . . . . . . . . continued
Diaphragm- or bladder-type — welded gas tight with a
rubbermembranetoseparatethetankpressurizingairand
thewater.Maybelocatedatanypointinthesystem,butmost
oftenfoundneartheboiler.
• Systemswiththistypeofexpansiontankrequireatleast
oneautomaticairvent,preferablylocatedontopofanair
eliminator,asshowninexamplesinManualSection 3,
page 10.
2. Ifreliefvalvehastendedtoweepfrequently,theexpansion
tankmaybewaterloggedorundersized.
Closed-type tank—tankismostlikelywaterlogged.Install
atankttingifnotalreadyinstalled.Thenchecklllevelper
ttingmanufacturer’sinstructions.Ifllleveliscorrect,check
tanksizeagainstmanufacturer’sinstructions.Replacewitha
largertankifnecessary.
Diaphragm- or bladder-type—rst,checktanksizetobe
sureitislargeenoughforthesystem.Ifsizeistoosmall,add
additionaltank(s)asnecessarytoprovidesufcientexpansion.
If tank size is large enough, removetank from system
and check charge pressure (usually 12 psig for residential
applications).Iftankwon’tholdpressure,membranehasbeen
damaged.Replacetank.
Boiler relief valve
1. Inspect the relief valve and lift the lever to verify ow as
in the following warnings, excerpted from a relief valve
manufacturer’s warning label. Before operating any relief
valve,ensurethatitispipedwithitsdischargeinasafearea
toavoidseverescaldpotential.ReadManualSection 3, page
10,beforeproceedingfurther.
2. Afterfollowingtheprecedingwarningdirections,iftherelief
valveweepsorwillnotseatproperly,replacethereliefvalve.
Ensurethatthereasonforreliefvalveweepingisthevalve
andnotover-pressurizationofthesystemduetoexpansion
tankwaterloggingorundersizing.
1. ReviewtheUser’sInformationManualwiththeowner.
2. Emphasizetheneedtoperformthe maintenanceschedule
speciedintheUser’sInformationManual(andinthismanual
as well).
3. Remindtheowneroftheneedtocallinalicensedcontractor
shouldtheboilerorsystemexhibitanyunusualbehavior.
4. Remindtheownertofollowthepropershutdownprocedure
andtoscheduleanannualstart-upatthebeginningofthe
nextheatingseason.
The boiler contains ceramic fiber and fiberglass
materials.Usecarewhenhandlingthesematerials
per instructions on page 39ofthismanual.Failure
to comply could result in severe personal injury.
1. Shut down boiler:
• Follow“ToTurnOffGastoAppliance”instructionsonboiler
and “OperatingInstructions”.
• Donotdrainboilerunlessitwillbeexposedtofreezing
temperatures.Ifusingantifreezeinsystem,donotdrain.
2. Follow shutdown procedure.
3. Remove venting system connection to boiler.
4. Removetopjacketpanel.Turnbackinsulation.
5. Remove ue collector. Clean sealant from assembly and
sections.
6. Remove radiation plates hanging between sections.
7. Removeburnersfrombase. Brushandvacuumburners to
removealldustandlint.Verifythatallburnerportsarefreeof
debris.
8. Placenewspapersinbaseofboilertocollectsoot.
9. Cleanbetweensectionswithwireuebrush.
10.Remove newspaperand soot.Vacuum or brush base and
surrounding area.
11. Reinstall radiation plates.
12.Replacecollectorbox/transitionassembly.Sealwithsealant.
Obtain gas-tight seal to prevent flue gas spillage and carbon
monoxideemissions,resultinginseverepersonalinjuryordeath.
13.Replaceinsulationandjackettoppanel.
14.Start up boiler followingSection 6, pages 15–17 of this
manualandtheboiler“OperatingInstructions”,pages 23 and
24.Excessivesootingindicatesimpropergascombustion.If
found,checkforpropercombustionandmakeanynecessary
adjustments.
o Cleaning boiler heating surfaces
SafetyreliefvalvesshouldbereinspectedATLEAST
ONCE EVERYTHREEYEARS, bya licensed
plumbing contractor or authorized inspection
agency, to ensure that the product has not been
affected by corrosive water conditions and to
ensure that the valve and discharge line have not
been altered or tampered with illegally. Certain
naturally occurring conditions may corrode the valve
or its components over time, rendering the valve
inoperative. Such conditions are not detectable
unless the valve and its components are physically
removed and inspected. This inspection must
only be conducted by a plumbing contractor or
authorized inspection agency — not by the owner.
Failuretoreinspecttheboilerreliefvalveasdirected
couldresultinunsafepressurebuildup,whichcan
result in severe personal injury, death or substantial
property damage.
Following installation, the valve lever must be
operatedATLEASTONCEAYEARtoensurethat
waterwaysare clear. Certain naturally occurring
mineral deposits may adhere to the valve, rendering
it inoperative. When manually operating the lever,
waterwilldischargeandprecautionsmustbetaken
to avoid contact with hot water and to avoid water
damage.Beforeoperatinglever,checktoseethat
a discharge line is connected to this valve directing
the owof hot water from the valve to a proper
placeofdisposalotherwiseseverepersonalinjury
mayresult. Ifnowaterows,valveisinoperative.
Shutdownboileruntilanewreliefvalvehasbeen
installed.
o Review with owner