Operating instructions

INSTALLATION
Please refer to the contract arrangement and site instructions as applicable.
It is recommended that a concrete foundation (to take foundation bolts – not
supplied) should be provided for the machine to be mounted on
Before completing the installation, check that the main mixer frame is level with a
spirit level. Packings should be inserted as required under the main frame.
Check that the pan is seated and that the pan rack and drive gear are in mesh..
Also check that all the blade clearances are in line with the maintenance
instructions.
On connecting to the power supply, the wiring diagram must be referred to.
Note:- it is recommended that the mains electrical supply is taken via an
earth leakage circuit breaker.
The wiring is correctly connected to the motors when the pan and star drive
rotate as follows:-
The mixing pan and mixing star rotate anti-clockwise when looking from the
top.