Technical data

32
Plume management system options
Plume management system
60mm dia. plume management kit
1 x terminal bend
1 x extension 500mm
1 x outlet assembly
1 x clamp pack
Part No. 7 716 191 086
Components Part No. Description
60mm diameter
7 716 191 086 Plume management kit
7 716 191 087 Extension (1,000mm)
7 716 191 088 90º bend
7 716 191 089 45º bend (pair)
7 716 191 176
Plume management
terminal guard round
500mm (M)
Standard plume management system
The flue terminal outlet has built-in stops which limits the
rotation for horizontal fluing, allowing the condensate to
run back into the boiler for safe disposal. Do not attempt to
force beyond the limit stops.
All plume management sections must rise by at least
173mm per metre (10º) from the terminal to ensure that
condensate flows back into the boiler.
Opening in building
e.g. window
Direction of
flue discharge
Min. 1,500mm
Opening in building
e.g. window
Direction of
flue discharge
Min. 1,500mm
Re-directing flue discharge from a 60mm dia.
plume management outlet
Accessories