- Xantrex Sine Wave Plus AC Conduit Box (ACCB) Owner's Guide Owner's Guide

Pre-installation
975-0046-01-01 1–7
Pre-installation
Location
Be sure to allow sufficient space for the ACCB to be mounted directly
adjacent to the inverters AC side. Also consider the additional weight
and ventilation space requirements of the ACCB.
Ventilation Requirements
Minimum clearance for ventilation around ACCB must be at least
6 inches (152 mm) at the end and at the top. The minimum clearance is
needed to prevent recirculating hot air from the inverters exhaust (DC
side) from going back into the inverters intake (AC side).
For maximum ventilation, 12 inches (305 mm) is recommended around
the top.
Please refer to the Sine Wave Plus Inverter/Charger Owners Guide for
additional location considerations.
WARNING
Ensure that no DC voltage is being supplied to the inverter and that no AC
voltage is present on the AC wiring. Failure to do so could cause serious injury or
death.
Figure 1-4
Clearance Requirements for Ventilation
DD
Set Inverter
OFF SRCH ON CHG
S ine Wa ve Plus Inve rt er / Charge r
AC Conduit Box
ON
OFF
ON
OFF
6" (152 mm)
Minimum Required
6" (152 mm)
Minimum Required
12" (305 mm)
Recommended