(10) Locate the parts to assemble
the floor joists.
(12) Repeat with all the joists ex-
cept four, as shown here. Then lay
out all the joists.
Note: Alternate all the joists as
shown.
(11) Push joists tightly together,
and align the OSB scabs flush with
the floor joists. Then; nail the OSB
scab, using twelve 2” nails per
Scab.
Flip the joist, then repeat on oppo-
site side.
Assemble Floor
(16) The 6” dado grooves should be
placed at the garage door sill.
(17) Attach the band board, using
3” screws, through the pre-drilled
holes. Make sure the floor joists are
flush with the band board as shown.
(18) Screw the rest of the band-
boards into floor joists.
Important! Band board splice
needs to be tight.
(13) Finish laying the joists and
band boards out as shown.
Note: Garage door sill consists of
four joists nailed together.
(14) The band boards have dado
grooves precut to ensure proper
joist placement.
The narrow grooves should
both be placed at the splice.
(15) The wider grooves should be
placed at the ends.
(866) 210-9273 - info@yardcraft.com