Assembly Manual

x16
1-1/2" (3,8 cm)
45
GABLE UNITS
PARTS REQUIRED:
x2 x2
Flush
Primed
side up
Primed
side up
2-9/16"
(6,5 cm)
1-3/4"
(4,4 cm)
1-3/4"
(4,4 cm)
1-1/2"
(3,8 cm)
Nails
1-1/2"
(3,8 cm)
Nails
PWA (on  at)
AO
PVA (on  at)
AO
Orient parts on  at as shown. You will build TWO assemblies.
Place LEFT front gable panel as shown and secure using 1-1/2" nails as shown.
1
BEGIN
2
3
Place RIGHT front gable panel  ush to left panel. Secure using 1-1/2" nails as shown.
Repeat Steps 1 - 2 to build second gable unit.
You have  nished assembling your gable units.
FINISH
Flush
x2
2 x 4 x 10" (5,1 x 10,2 x 25,4 cm)
PWA
x2
2 x 4 x 6" (5,1 x 10,2 x 15,2 cm)
PVA
AO
x2
2 x 4 x 22-1/2" (5,1 x 10,2 x 57,1 cm)
TEMPORARY SUPPORT