Assembly Manual
46
GABLE UNITS
PARTS REQUIRED:
3" (7,6 cm)
x4
x2 Gable Units
Set gable unit on top plate SZ. BE SURE GABLE UNIT IS CENTERED ON WALL BEFORE NAILING.
First, hold gable unit secure with one 2" nail on each side, then secure with two 2" nails
at top of gable panels into end rafter (Fig. A).
Continue nailing lower edge of panels into top plate using 2" nails 6" apart as shown
1
BEGIN
Install both gable units the same on both gable walls. Measure 2-9/16" down from top plate and mark
at each side as shown (Fig A).
You have nished installing your gable units.
FINISH
2" (5,1 cm)
x40
PVA
3"
(7,6 cm)
Screws
Fig. B
TOP PLATE (SZ)
SZ
3"
(7,6 cm)
Screws
NAIL FIRST
2" (5,1 cm)
NAIL FIRST
2" (5,1 cm)
2" (5,1 cm)
Nails
6"
(15,2 cm)
Fig. A
TOP PLATE
2-9/16"
(6,5 cm)
Measure and
Mark
2-9/16"
(6,5 cm)
Measure and
Mark
On the inside, secure gable unit with 3" screws toe-screwed into SZ at an angle as shown in (Fig. B).
2