6.5.2. Boiler base
If the floor of the boiler room is moist or loose, a sufficiently high boiler base must be provided. Moisture does not
go well with electrical equipment!
Otherwise, no base is needed for the unit.
6.5.3. Boiler support
It is possible to mount the boiler on vibration dampers (available as option) to reduce noise transmission caused
by vibrations.
VG 350-450 274 mm
VG 500-600 346 mm
Dimensions and positioning of the vibration dampers
(further dimensions see chapter 4.3)
When the condensing unit has been placed correctly, the vibration dampers are put underneath it. To do this, the
unit is lifted by approx. 5 cm on one side using a hoisting device. Next, half of the vibration damper elements are
placed underneath, and the elements must lie flush with the base frame at the front. In addition, make sure that
the elements are flush with the inner side of the base frame. The unit can now be carefully lowered onto the
elements. The remaining vibration dampers are now placed underneath the opposite side of the unit in the same
way.
Afterwards, you can start installing the connection tubes on the water and flue gas side.
Attention! Once the unit is filled up, it will come down by further 2-3 mm.
6.6. Installing the unit
The unit is only allowed to be installed by authorised specialist personnel. Such personnel are familiar with the
unit and know the special aspects relating to its installation.
Each module (burner, gas line, fan, casing, boiler control panel, etc.) is supplied with its own installation
instructions. We recommend that you keep them together with these instructions. Some of these instruction
documents are also required for startup, subsequent operation and maintenance (gas compact unit, control
panel, governor, ignition electrode, O
2
sensor).
The boiler casing may only be assembled after the boiler has been completely connected and the heating