Instruction Manual

System 182 Installation
3 - 13
ba76024e01 02/2012
Preparing the cable
ends
Fig. 3-11 Prepared cable end
Connecting the cables The SNCIQ and SNCIQ/UG cables are connected to the terminal strip
in the same way as the SACIQ sensor connection cable (see
section 3.4.5):
1 Cut off the cable to the required length.
2 Remove approx. 45 mm of cable insulation (in the case of the
SNCIQ/UG earth cable, remove both the inner and
outer
insulation).
3 Only for the SNCIQ/UG earth cable:
strip the outer insulation for a further 35 mm.
4 Shorten the exposed shielding braid up to the cable sheath.
5 Shorten the two fillers (plastic inlays) up to the cable sheath.
6 Bare the red and green wires and fit them with wire end
sleeves.
7 Fit the filler stranded wire with a wire end sleeve.
SNCIQ
SNCIQ/UG
approx. 35 mm approx. 45 mm
approx. 45 mm
1 Open the enclosure of the Universal Transmitter or
MIQ module.
2 Select a free SENSORNET connection. At the same time, look
out for the SENSORNET designation on the label on the
bottom of the enclosure.