Unit installation

5
1.4.3 Installing the appliance
installed the 5 anti-vibration studs (supplied, see §1.1.2),
put onto a stable, solid (concrete slab type) and level surface,
preserve from risks of flooding due to condensation produced by the appliance whilst it is operating
(see §1.4.4)
1.4.4 Hydraulic connections
The connection shall be by Ø 50 PVC pressure pipe, from a by-pass , to the swimming pool filter
circuit, after the filter
and before the water treatment :
PF
Hydraulic circuit pressure
Fittings
= inlet
= outlet
Average water
flow-rate
head
loss
test operating
bar bar m³/h mCE
6M
3 1.5
half union Ø50
fitting to stick
(see
parts and
§1.1.2)
3 1.3
8M
4 1.4
11M
5 1.5
13M
6 1.5
15M
6.5 1.1
Water treatment, recommended parameters:
- free chlorine: maximum 2.5 mg/l,
- total bromine: maximum 5.5 mg/l,
- pH : between 6.9 and 8.0.
The water treatment system (chemical or electro-physical disinfection) must be installed
downstream from the heat pump (see installation below), and must be compatible
with it (check with the manufacturer).
Possibility of fixing the appliance to the ground, using the holes in the base of the
appliance.
A diagram of drilling is available to the back of the packing box.
EN
Fixing holes