INSTALLATION
1. Zurn Light Commercial Grease Interceptors
should be installed as close as possible to the
fixture being served. Always install where there
is easy access for cover removal and cleaning.
2. A flow control must be installed as close as
possible to the underside of the fixture. The
flow control must be installed with the vent or
(air intake) on the downstream side of the orifice
plate. The vent connection is positioned to the
top of the flow control fitting and piped upward
higher than source of water, or to building vent
system
3. It is recommended that a cleanout tee be
installed before the flow control to access the
flow control orifice and clear debris.
4. The cleanout plug should be installed over the
outlet of the interceptor.
5. The interceptor is to be installed using no-hub
couplings.
6. Outlet piping should be connected to the
sanitary drain, and pipe size should be equal
to or larger than the inlet piping. Outlet pipe
should also be vented so the interceptor is not
siphoned.
7. Solid waste should not go into an interceptor.
Food grinder waste and other solids should
be captured in the sink or by a solids interceptor
before reaching the grease interceptor.
Zurn Light Commercial Series Grease Interceptors #2700 consist of a interceptor rated at
( ) gpm and a properly sized flow control fitting.