Click the respective buttons to pause and resume the Rebuild.
Click the Abort button to stop the Rebuild. After an abort, click the Restart button
to start the Rebuild from the beginning (zero percent).
Scheduled
To schedule a Rebuild:
1. Click on the Logical Drive View icon in Tree View.
2. Click on the Logical Drive icon of the logical drive you want to rebuild.
3. Click on the Rebuild tab in Management View.
4. Select the physical drive you want to rebuild.
Available drives have a black frame. Selected drives have a red frame.
5. Click on the Enable option.
6. From the dropdown menus, select a start time.
Start time is based on a 24-hour clock.
7. Click in Start At field to display a popup calendar.
8. Click on the start date in the calendar or enter a date manually.
9. Click the Schedule button.
Cancel a Schedule
If you want to cancel the scheduled Rebuild, do the following:
1. Click on the Logical Drive View icon in Tree View.
2. Click on the Logical Drive icon.