Technical data

Prepare the ground mount hardware in the mount hardware kit by sorting all bolts, nuts, and
flat washers into separate sections as shown in Figure 6.
Wax two sides of each galvanized bolt with the stick wax provided. This allows a smooth
installation of each galvanized bolt as shown in Figure 7.
Set Azimuth Tube Weldment (7542711) on the ground near the pedestal. Put (7542635)
bearing pad on top of it, line up the bolt holes with the slots, place Tube Weldment
(7545086) on top of the pad secure it with (4) x 5/8-11 hardware. Snug Tighten the bolts
Installation Procedures
Step 3
Step 4
Step 5
15
Figure 6
Figure 7
Bearing Pad
Tube Weldment
Azimuth Tube
Weldment
Figure 8-A